The Marcellus Road project will officially be beginning with the closing of the road from Sept. 21 through Nov. 16, 2015. This will be for the first phase of the three phase project set to be finished in June of 2016.
The work on the road will be from Tokio Road to Davis Road.
The first phase consists of earthwork for the shoulder widening of the road, replacing culverts and the realignment of the North side of Marcellus at Davis and Rocky Ford Road, this will cost an estimate of $420,000.
The biggest challenge for this project was the funding. The Adams County Engineer Scott Yaeger estimated...